What order to do a bathroom in

Most bathroom problems are ordering problems: the filler that needed its pipe in before the floor went down, the frame that had to be in the wall before the tiler came. This is the order a good fitter works in, and what you need to have bought before each stage starts.

Print it, or bring the room measurements and we'll walk it with you

Latest offers & newest designs

New stock lands most weeks and offers change — both go straight onto our Facebook and Instagram. Follow along, or ring the showroom for a price on your quantities.

1. Strip out and first fix

The old suite comes out and the plumber and electrician run pipes and cables to where everything new will sit. This is the stage that locks in your decisions, because moving a pipe after the tiles are on means taking tiles off.

  • Decided and bought: WC type and frame, basin and vanity position, bath or tray size
  • Decided: concealed or exposed shower valve, and where the controls go
  • Decided: floor-standing bath filler, because its pipe goes in the floor now
  • Decided: towel rail position and whether it is dual fuel
  • Electrics: shower circuit, mirror spur, shaver socket, all by a registered electrician
  • Soil pipe and waste positions confirmed against the pan and tray you have chosen

2. Floor and walls prepared

Everything the tiles will sit on. Skip it and the tiling fails later, however good the tile.

  • Floor levelled: within 3mm over a 2m straightedge for large format
  • Timber floors boarded with a tile backer or a decoupling membrane
  • Walls checked for flatness and for anything loose
  • Plasterboard primed; tile backer board where the weight needs it
  • Bath or tray in and levelled, so the tiles can finish down onto it

3. Tanking the wet areas

Waterproofing the shower area and around the bath before any tile goes on. A tile is not waterproof; the grout certainly is not. The tanking behind them is what keeps the water out of the wall.

  • Tanking kit or liquid membrane to the shower area and bath surround
  • Tape into the corners and around the tray
  • Wetroom former and drain, if it is a tiled floor shower
  • Left to cure for as long as the tin says, not as long as the tiler has

4. Tiling

Most fitters tile the walls first, leaving the bottom row off, then the floor, then the bottom row so it sits neatly over the floor tile. Large format goes on a flexible S1 adhesive with the back of each tile buttered.

  • Tiles, with 10 to 15% wastage for straight lays, 20 to 25% for herringbone or diagonal
  • Adhesive: roughly one 20kg bag per 4 to 5 square metres for small formats, 2.5 to 3 for large format back-buttered
  • Grout, in a colour chosen against the actual tile
  • Trims for exposed edges, in the brassware finish
  • Levelling clips for anything 60 × 120 or bigger
  • Spacers, and a sealer for polished porcelain before grouting

5. Second fix

The sanitaryware and brassware go on. This is when a mismatched waste or a filler in the wrong finish shows up, so it is worth having laid every piece out together before this day.

  • WC pan hung on its frame and the flush plate fitted
  • Basin and vanity, taps and wastes
  • Shower valve trim, riser or rigid riser, head and handset
  • Enclosure or screen fitted to the tray
  • Radiator or towel rail connected
  • Mirror, cabinet and accessories

6. Silicone and snagging

Last, and the thing that is skimped on most. Anti-mould silicone to every tile-to-tray, tile-to-bath and corner joint, and nothing used until it has cured.

  • Anti-mould sanitary silicone, in a colour matching the grout or the tile
  • Expansion joints where the floor meets the wall
  • Grout checked and sealed if it is cement-based
  • Left dry for 24 hours before the first shower

If you are fitting this yourself, bring the room measurements and your plan in and we will go through this list against it at the counter. It takes twenty minutes and it is the difference between one trip and four.

Questions people ask

Straight answers

Do you tile the walls or the floor first?
Most fitters tile the walls first, leaving the bottom row off, then tile the floor, then fit the bottom row of wall tiles so it sits neatly over the edge of the floor tile. That hides the floor tile edge and means the floor is not walked on while the walls are done. Some fitters floor first and protect it; both work. What matters is that the bath or tray is in and level before either starts.
What do I need to have bought before the fitter starts?
Everything that goes in the wall or the floor: the WC frame, the shower valve, the bath or tray, the bath filler if it is floor-standing, and the tanking. The tiles, adhesive and grout need to be on site before tiling day. Taps, basin, mirror and accessories can arrive later, but having them all laid out together before second fix is how you catch a chrome waste on a brass tap. Bring your fitter's start date in and we will work the list backwards from it.
How long does a bathroom refit take?
A straight like-for-like swap with new tiles is usually a week to ten days for a good fitter. Moving the toilet, going wall-hung, or forming a wetroom adds days for the first fix and the tanking cure time. The common delay is not the work, it is waiting for a part that should have been on site at the start, which is why the list above is ordered the way it is.
Can I do any of it myself?
Strip out, yes. Painting and the accessories, yes. Tiling a floor or a splashback, with care. Anything electrical in a bathroom needs a registered electrician, and in England and Wales it is notifiable work. Tanking and the shower installation are where a mistake costs the most, because the leak shows up in the ceiling below six months later. If you are doing part of it, do the parts you can see.

Not sure how much you need?

Use the calculator, or bring your measurements in and we'll work out metreage including wastage plus the adhesive, grout and trims to go with it.